A technician and co-owners assess a collective heat pump
Works and equipment

Collective heat pump: what should be checked before the vote?

A heat pump cannot be selected from its stated output alone. In an existing apartment building, feasibility first depends on real heat demand, the heating circuit, available electrical capacity, location and noise.

Approving a specific machine should not be the first step. The co-ownership must start by defining the required service: space heating only or domestic hot water as well, full replacement or supplementary system, timetable and comfort level. A feasibility study turns those questions into testable assumptions and prevents quotations based on different versions of the building from being compared.

How much heat does the building actually require?

Past bills provide an initial indication, but they need to be adjusted for weather, occupancy and completed renovation work. A professional should estimate the building’s heat losses and peak demand. An oversized machine may operate in short cycles; an undersized one may rely excessively on supplementary heat during cold periods.

The study should state whether domestic hot water is included and how peaks will be covered. It should also show the effect of future improvements such as roof insulation. The co-ownership can then decide whether to coordinate the works or size the system for the building as it currently stands.

Is the existing heating circuit compatible?

A heat pump is generally more efficient when the water temperature required by the radiators remains moderate. The temperature needed in the least favourable flats must therefore be measured or calculated; looking only at the boiler is not enough. Radiators may need adapting, the circuit balancing and the controls revising.

The plant room must have space for indoor units, tanks, pumps and accessories. The quotation should explain how supplementary heating works and what happens if the system fails. If several scenarios are proposed — prior renovation, a non-fossil hybrid system or full replacement — their consumption should be calculated using the same assumptions.

Have location, noise and electricity been studied?

For an outdoor unit, location affects performance, maintenance and the noise heard by neighbours. A figure on a technical sheet is not enough: distance, façades, windows and acoustic reflections must be considered. Maintenance access and condensate drainage must also be planned.

For an air-to-water heat pump whose outdoor unit is installed in the common parts, an acoustic requirement must be checked before installation. The acoustic power L_W of that unit, as shown on its ErP label, must not exceed 48 dB(A) up to 5 kW, 51 dB(A) above 5 kW and below 12 kW, and 55 dB(A) from 12 kW. If the model exceeds that ceiling, the value taken into account may be reduced by sound-insulation equipment, provided that the reduction in dB(A) is guaranteed and stated in its technical data. If the ceiling is still not met, a second route is open: the noise level caused at the boundary of the nearest neighbouring buildable plot must not exceed 40 dB(A), and proof is provided by an acoustic assessment drawn up before installation, exclusively using the calculation tool “Calcul du niveau de bruit / Schallrechner” made available by the minister (Law of 24 July 2026 on the grant scheme for the promotion of sustainability, the rational use of energy and renewable energies in the housing sector, Annex II, point 7° — Mémorial A No 416 of 7 August 2026).

Compliance with this requirement is established during acceptance, to which every new installation is subject (Law of 17 August 2026 on the operation of heat pumps, Article 5 — Mémorial A No 463 of 14 September 2026 — and Grand-Ducal Regulation of 17 August 2026 on the arrangements for the operation of heat pumps, Article 1 — Mémorial A No 464 of 14 September 2026).

Complying with these limits does not settle the question of the neighbours: a disturbance exceeding the normal inconveniences of neighbourhood can still be sanctioned (Article 544 of the Civil Code, as replaced by the Law of 2 July 1987 — Mémorial A No 61 of 1987). Depending on the solution chosen, a building permit, the municipal building regulations or, for certain variants, the regime for classified establishments may also apply: to be checked before the meeting is convened.

A large collective installation may require a check of the available electrical power and the grid connection. In multi-unit buildings, Klima-Agence recommends checking beforehand with the electricity network operator that the network is designed for the operation of a large heat pump. The co-ownership should obtain that answer — most often through the installer — before treating the quoted price as complete.

What file should be presented to the general meeting?

The file should compare a small number of scenarios on the same basis: investment, building adaptations, estimated consumption, maintenance, assumed service life and price assumptions. Possible grants should be shown separately with their conditions and timing. They reduce a cost if the project qualifies; they do not make a technically unsuitable solution appropriate.

The grant scheme is set by the Law of 24 July 2026: Article 6 for heat pumps, Annex II for the technical requirements. The grant is increased where the order date falls between 1 January 2026 and 30 June 2027 inclusive and the invoice is issued no later than 31 December 2028 inclusive: the date on which the general meeting authorises the works and the syndic places the order therefore determines the amount, and a syndic who learns of this too late can no longer do anything about it. Annex II also makes the grant conditional on the company that put the installation into service having submitted the acceptance request to the Chambre des Métiers: missing the acceptance means losing the grant. It further requires, for a collective project, a separate or integrated electricity meter and a heat meter, hydraulic balancing of the network at installation and, in an existing building, a buffer tank of at least 30 litres per thermal kW, except for installations with power modulation. The amounts and the detailed conditions are to be confirmed at the time of the project.

Replacing a collective heating system with a heat pump in the common parts falls under Article 16 of the Law of 16 May 1975: replacement works involving an improvement or a transformation of existing items of equipment (point d, added by the Law of 22 April 1985), energy renovation works (point e) and the installation of facilities producing energy from renewable sources in the common parts (point g), the last two of which were added by the Law of 30 June 2022. Article 17, point c), as replaced by the same law, expressly excludes them from the double majority of Article 17 (a majority of the members of the co-owners’ association representing at least three quarters of the voting rights).

The decision is adopted by a majority of the votes of all the co-owners, and not only of those present (Article 16, first paragraph). If that majority is not reached, a new general meeting decides by a majority of those present or represented (Article 16, final paragraph). Where the co-ownership regulations place these expenses on certain co-owners only, those co-owners alone vote, with a number of votes proportional to their share. Once the decision has been duly and expressly taken, no co-owner may obstruct the carrying out of the works, even inside their private parts (Article 28, as amended by the Law of 22 April 1985).

The decision may also be taken outside a meeting, by written consultation, subject to three cumulative conditions: the boiler must be unfit for service and must be replaced by a more advanced installation, the syndic must have submitted all the necessary assessment material, in particular the cost of the works, and the use of this procedure must be authorised beforehand by the owners’ council (conseil syndical), where one exists (Article 14, point 1, as resulting from the Law of 22 April 1985). A boiler that is still in working order and is replaced by choice goes through the general meeting.

Since its entry into force on 18 September 2026 (the fourth day after its publication, under Article 4 of the Law of 23 December 2016 on the Official Journal of the Grand Duchy of Luxembourg), the Law of 17 August 2026 on the operation of heat pumps has applied to every fixed heat pump, whatever its thermal output, provided that it regulates the indoor climate of the building. Only an installer holding the required business permit (“autorisation d’établissement”), or a foreign service provider lawfully carrying out such services in Luxembourg, may install, modify or maintain it (Article 4). Every new installation is subject to acceptance, an obligation that has existed since 19 September 2025: it results from the Grand-Ducal Regulation of 13 August 2025 on the arrangements for the acceptance of heat pumps (Mémorial A No 395 of 15 September 2025), repealed and taken over by the 2026 law and its implementing regulation, which add periodic inspection, decommissioning and fines. The company that put the installation into service submits the request to the Chambre des Métiers within the month, and the acceptance takes place within three months of the notification (Article 5). The operator — in a co-ownership, the co-owners’ association, through its syndic — must then have it inspected: no later than 18 September 2028 for an existing installation, between one and two years after commissioning for a new installation, then every four years from the date of the first positive inspection (five years if the installation is monitored remotely, three years above 290 kW of effective rated output) (Article 6). Decommissioning gives rise to a declaration to the Environment Agency (Administration de l’environnement), made by the company that dismantles or empties the installation (Article 7). An operator who fails to have the installation inspected faces an administrative fine of 75 to 5,000 euros; fines of 500 to 750,000 euros target companies that carry out work without the required authorisation or certification (Article 12).

The proposal put to the vote should identify the equipment, related works, contingency budget, financing and supervision mandate. The permits specific to the chosen solution and the grant conditions applicable to this file must be confirmed for the actual case by the professionals. The decision then becomes understandable: owners are voting on a defined, checked and comparable system, not on a promise of savings.

This page is provided for information only and does not constitute legal advice. The official Luxembourg texts prevail; if in doubt about a specific situation, consult a professional.

Request a free quote Call